Showing posts with label NC12. Show all posts
Showing posts with label NC12. Show all posts

Wednesday, January 16, 2013

A Drudge of a Dredge

As of right now, no work is going on N.C. 12 at Mirlo Beach because of a mechanical issue with the dredge pump.  The pump is not generating enough pressure to keep its lines from clogging with sand.  A part needed to fix the issue has been ordered and will be shipped overnight.  The repair is expected to be made tomorrow.


The dredge is the large red piece of heavy equipment in background
The gap between the sandbags placed at the north and sound ends of the highway is now approximately 100 feet wide.  Our engineers calculate that it will take 200 sandbags to fill in the gap. However, crews can’t resume the sandbag installation until the malfunctioning dredge is fixed.  The dredge is used to remove water and sand from the work site and sand collected by the dredged is then used to fill the sandbags.

Tomorrow, the plan is to begin hauling sand from Avon to fill in the trench between the sandbags and edge of the road. This will take approximately two days. Once the trench is filled, it will protect the edge of the road any overwash  gets through the sandbags. The trenches need to be filled before crews can begin covering the sandbags with sand to rebuild the dunes.

Weather on Friday will be windy with an “ugly”ocean.   Winds reaching 20-30 miles per hour could batter the Outer Banks starting Thursday night  and continuing into Friday. High surf driving by swells of 8-11 feet could become an issue, depending on winds and high tides.  

Tuesday, January 8, 2013

Sandbag Progress

N.C. 12 Sandbag and Dune Rebuilding Update
As of Sunday, Jan. 6, crews had approximately 620 sandbags left to install in the effort to rebuild the dunes near Mirlo Beach in the wake of Hurricane Sandy.  Weather permitting, this work could be complete as early as Jan. 18.  Once all the sandbags are in place, they will be covered with approximately 6-8 feet of sand. The sand used for filling sandbags and dune reconstruction is trucked in from a sand pit in Avon.

Ferry Adds Night Departures
The NCDOT Ferry Division is adding two night departures at its Swan Quarter-Ocracoke route, beginning Wednesday, Jan. 9, to assist travelers while the Hatteras ferry channel is dredged. These runs are in addition to the current winter schedule of two departures daily from each side. The extra night departures will continue until the Hatteras-Ocracoke schedule returns to normal.

For the past several weeks, ferry operations have been suspended daily during low water at the Hatteras-Ocracoke route. Shoaling in the channel has been an ongoing issue, but Hurricane Sandy, two back-to-back Nor’easters and several winter wind storms have contributed to the problem. The U.S. Army Corps of Engineers is working to resolve the situation, as the channel falls under federal jurisdiction. The USACE has issued a dredging contract to address the channel shoaling, and work is under way, but several weeks could pass before dredging alleviates the problem


Shoaling, Dredging, and Ferries: A Q&A




We’ve gotten several questions and comments about the shoaling situation at the Hatteras-Ocracoke ferry route.

To help address them in a clear and concise way, we’ve created the Q&A below.

Q: Does the Swan Quarter ferry have the capability of running at night?

A: The Swan Quarter-Ocracoke route can operate at night.

Q: Why hasn't the Ferry Division added additional runs from Swan Quarter to give Ocracoke residents (and tourists) a reliable access route to the northwest?

A: We’re adding night runs, beginning Wednesday, Jan. 9, with a 7 p.m. departure from Ocracoke and a 10 p.m. departure from Swan Quarter.

Q: Why has the ferry division not allowed Ocracoke residents free passage to Cedar Island and Swan Quarter at times when the Hatteras ferry is not operating?

A: The current toll exempt policy allows Ocracoke residents with appropriate supporting documentation to travel toll free to doctors’ visits via both Pamlico Sound routes. This addresses elderly, pregnant and diabetic residents, as well as those with court appointments and Hyde County government workers.

 Q: Is it true that the Hatteras-Ocracoke ferry route will be totally shut down for a while due to dredging?

A:  Once the contracted dredge gets to the “hot spots,” especially at channel marker #10, there may not be sufficient room or water depth for the ferries to get around the dredge. If we must suspend operations for a lengthy period of time while dredging is under way, we will notify the public in advance. The Ferry Division will continue to provide service, when the water fluctuation allows. If the channel is completely shut down, we have the ability to add additional departures at Swan Quarter to accommodate the citizens of Ocracoke.

Q: Why did the dredging not begin with the trouble spots in the ferry channel?

A:  The Ferry Division has been working closely with the US Army Corps of Engineers on the dredging issue. However, the Corps has contracted the work to a private company, and we do not have the authority to tell the Corps or the contractor how to perform the work.

Q: Please let us know when suspensions at Hatteras occur, in order to plan travel?

A:  Currently the pattern at Hatteras seems as follows: early runs in the morning are made, then operations suspend from about 7:30-8:00 a.m. until noon-1 p.m.. Then, operations resume again and then suspend around 6 p.m. until the late night departures of 11 p.m. and midnight.

The Ferry Division posts updates on suspensions and resumptions on the NCDOT NC 12 Facebook page and Twitter. The Tweets also go directly to the ferry website, www.ncferry.org. We have positioned a digital sign at Whalebone Junction, alerting drivers to possible suspensions and made 511, NCDOT’s toll-free travel information line, aware of the situation, as well.

If you have further concerns, comments or questions, please send them directly to the Ferry Division via the website Contact Us forum or call the Morehead City office directly at (252) 726-6446.

Monday, December 10, 2012

A Lifeline

The Outer Banks Voice did a nice profile of the emergency ferry service.  Thanks to the good folks there, for this and for all they do for their community!


Friday, December 7, 2012

We know it's interesting, but...

....we don;t want anyone to get hurt in the NC 12 work zones.  Not in your cars.  And not on foot.  We've had some folks venturing out to take pictures of the work, to get a higher view, etc. But as interesting as it it, with all the heavy equipment out there, and the debris and deep sand  it's just not safe.  We know you understand.  Thanks!








Thursday, December 6, 2012

Out of the mouths (and artistic eyes) of babes

Priceless.

We love you too, Jack!

One of several thank you letters
posted inside the temporary ferry terminal on the Rodanthe side of the emergency ferry route.  From Hatteras Elementary School


Wednesday, December 5, 2012

NC 12 Plan Q&A

Q&A about Hurricane Sandy Recovery Efforts along N.C. 12

We’ve gotten a variety of questions about our recovery plans along N.C. 12 in Dare County. We want to answer those questions, so you can better understand why we’re doing what we’re doing.

Q: Why are you rebuilding N.C. 12 in the same place?
A: We’re rebuilding N.C. 12 in the same location at the S-Curves, because it is the fastest way to restore access from Hatteras Island to the mainland. We know it hasn’t been easy for residents and visitors to use the emergency ferry route and the four-wheel drive route to get where they need to go. That is why we’re committed to reopening the highway to all vehicles as quickly as possible. Our goal is to have traffic flowing on N.C. 12 on or by Dec. 25.

Q: Are you considering beach nourishment at the S-Curves?
A: Yes. Beach nourishment is currently under consideration as we work to rebuild and reopen N.C. 12 near Mirlo Beach. We’re working with the U.S. Army Corps of Engineers to evaluate this option. No final decision has been made yet.

Q: Can you put down mats on the four-wheel drive route?
A: It is possible to put mats on the soft sand; however, they will only stabilize the route for four-wheel drive vehicles. The mats will not provide a surface stable or level enough for all-wheel drive and two-wheel drive vehicles. Therefore, we have chosen at this time not to use mats, because they would not greatly enhance the level of service we can provide, and they would take a great deal of effort to maintain.

Q: Can you put down gravel on the four-wheel drive route? Why not pave the four-wheel drive “sand road” and put dunes to the east of it?
A:  If we put down gravel or asphalt on the four-wheel drive route, we would be creating a permanent structure on Pea Island that is not inside our property lines. To do that, we would need to get special approval from a number of regulatory agencies. In addition, if we built a road on a new location, we would also need to build a temporary bridge at the overwash area to ensure access during storms. These combined steps would take far longer to implement and open to traffic than our current plan of rebuilding N.C. 12 in the same location, which should be complete on or by Christmas Day. Our goal is to reopen the highway as quickly as possible.

Q: Do you have long-term plans for the S-Curves?
A: Yes. In Rodanthe, the department is considering two options. The first one includes elevating N.C. 12 onto a bridge within the existing easement, which would end just north of the community center and not require beach nourishment. The second option is constructing an approximately 2.5-mile bridge that would extend into the Pamlico Sound and connect back to Rodanthe just north of the community center. These long-term solutions are currently moving through the environmental planning process required by the state and federal governments. We plan to award a contract for construction in the fall of 2013. 

Visit our new N.C. 12 webpage for more information.

We Have a Date!

Calm weather conditions have prevailed in Dare County and our crews have made significant repairs to N.C. 12 and we are now able to move to the next step - a   temporary solution to reconnect all traffic on Hatteras Island to points north of Mirlo Beach. This will be a multi-step process that will include installing sandbags, reconstructing dunes, and rebuilding the road near Rodanthe where Hurricane Sandy and a pair of Nor’easters damaged the highway.

What's Happening Now

Crews are currently placing 15-foot-long sandbags along a 0.4-mile section of N.C. 12 at the S-Curves just north of Rodanthe on Pea Island. In all, 1,800 new sandbags will go in to create a protective barrier between the ocean and the road. Once the sandbags are in place, we'll rebuild the dunes on top of the sandbags.

At the same time, broken pavement will be hauled off from this section of N.C. 12. After sandbags are installed at the most heavily damaged parts of the highway, crews will begin rebuilding the road where it was located before the series of storms hit. And as you know, all work is heavily dependent on the weather and tidal conditions.

Weather permitting, we hope to open the newly paved lanes of N.C. 12 to all traffic on or by Dec. 25. Until then, four-wheel drive vehicles must continue to pass through checkpoints at the temporary bridge on Pea Island and Mirlo Beach to travel between Hatteras Island and the mainland.

Motorists are reminded that any private vehicle larger than a one-ton truck cannot use the route in order to protect access and allow traffic to flow more efficiently. In addition, private trucks with trailers are not permitted. Two-wheel drive vehicles are not allowed on the route under any circumstance.
More information on N.C. 12 recovery efforts is available on our N.C. 12 Recovery webpage and N.C. 12 Facebook page. For the latest details on the emergency ferry route, as well as schedules for our regular ferry routes, call 1-800-BY-FERRY and press 1, or visit the NCDOT Ferry page.

Friday, November 30, 2012

Updates: Temporary Bridge, Rodanthe and The Emergency Ferry

What's Happened? What's Next?
Paving 
As you may know, paving at the temporary bridge was completed yesterday.  Replacement of guardrail is the only remaining work there and that should begin today or tomorrow.  A temporary signal with a one lane traffic pattern will be in place at the temporary bridge until the guardrail is completed.

Paving of the repaired spans on Bonner Bridge were completed on Monday.

 
In an effort to reduce the length of the closed areas that have to be managed, Dare County is moving the checkpoints south of the temporary bridge.  

All other work with the exception of guardrail at the temporary bridge is complete.


S-Curves
At Rodanthe, sandbag installation continues along the east side of NC 12.  The contractor is working from south to north.  Additionally, removal of damaged pavement is set to begin on Monday. 

Monday Ferry Schedule Note
  
On Monday, Dec. 3, the 10 p.m. emergency ferry departure from Stumpy point to Rodanthe will be delayed so that a davit cable for the lifeboat on the Motor Vessel Hatteras can be replaced.  More details.

Thursday, November 29, 2012

UPDATE: 4WD Access Opened Ahead of Schedule!

Our crew completed the maintenance work on the four-wheel drive access detour two hours ahead of schedule and it is now open to traffic!

Big, big kudos to the folks out there who worked hard to shore  up the access detour!

NOTE: The weight restrictions on the 4WD access that were initiated Tuesday ARE still in place.

Wednesday, November 28, 2012

4WD Closure set for Thursday

The large amount of traffic using the four-wheel drive access route on NC 12 at the S-curves, as well as the condition of the sand is forcing us to close the road tomorrow so that crews can  increase the stability of the sand on the north end of the route.  

The maintenance will also help reduce the likelihood of overwash on the access route as well. 

The four-wheel drive access will be closed Thursday, Nov. 29, from 9 a.m. to 4 p.m.

The traffic volume and sand conditions also forced NCDOT crews to implement vehicle size and weight restrictions.

Since the four-wheel drive route along N.C. 12 on Pea Island opened, a number of vehicles have gotten stuck in the sand and required a tow truck to get them out. This not only causes delays for the other vehicles using the route, but it also damages the makeshift road.

To help protect access and make traffic flow more efficiently, NCDOT is no longer allowing any vehicle larger than a one-ton truck to use the route. In addition, trucks with trailers are not permitted. Two-wheel drive vehicles are not allowed on the route under any circumstance.

Vehicles who do not meet the weight requirements and/or vehicles with trailers are becoming stuck in the sand, and this causes unnecessary back-ups as tow trucks and heavy equipment remove them.
 

Those of you who can use the route - please remember - the ride will be rough as you will be traveling over sand, damaged pavement and some water. On the sandy portions of the route, please follow lane markers.

Other important safety measures to take on the four-wheel drive access:

  • Only drive four-wheel drive vehicles with a high ground clearance. Cross-over four-wheel drive vehicles that are lower to the ground may get stuck in the rugged terrain;
  • If you drive at night, use extreme caution. There will are no lights staged along the route, so your vehicle’s headlights will offer the only way for you to see;
  • Drive slowly;   
  • Pay close attention to the temporary traffic signals; and
  • All four-wheel drive vehicles are encouraged to lower tire pressure to minimize the chances of becoming stuck.

Tuesday, November 27, 2012

New Weight Limits for 4WD Access



Since the four-wheel drive route along N.C. 12 on Pea Island opened, a number of vehicles have gotten stuck in the sand and required a tow truck to get them out. Sunday alone, 49 vehicles had to be towed. This not only causes delays for the other vehicles using the route, but it also damages the makeshift road.

To help protect access and make traffic flow more efficiently, NCDOT is no longer allowing any vehicle larger than a one-ton truck to use the route. In addition, trucks with trailers are not permitted.

New Schedule for the Emergency Ferry

MANNS HARBOR — The North Carolina Department of Transportation’s Ferry Division is reducing the total number of runs each day at the Stumpy Point-Rodanthe emergency route from 9 to 8 from each side. The change is to reduce costs and is effective Wednesday, Nov. 28.

The eliminated runs are those with the least amount of traffic and include the 8 p.m. departure from Stumpy Point and the 11 p.m. departure from Rodanthe. Those who use the emergency route are reminded to be patient, as priority status is still in effect.

The Stumpy Point-Rodanthe schedule will be as follows:
•    Departing Stumpy Point at 6 a.m., 8, 10, noon, 2 p.m., 4, 6 and 10 p.m.
•    Departing Rodanthe at 7 a.m., 9, 11, 1 p.m., 3, 5, 7 and 9 p.m.

The N.C. Ferry Division will reinstate these runs should travel demand warrant.

Emergency ferry information is available by calling 800-293-3779 (BY-FERRY) and pressing 1, via Twitter,on Facebook  and on the NCDOT.gov NC 12 page.