Showing posts with label Bonner Bridge. Show all posts
Showing posts with label Bonner Bridge. Show all posts

Wednesday, December 11, 2013

Underwater Surveys and Pile Tests on Completed on Bonner Bridge



Our crews completed several tests and surveys of the Herbert C. Bonner Bridge on N.C. 12 over the Oregon Inlet in Dare County today. These tests will provide crucial information to help evaluate the overall effectiveness of the sand placed in the area where erosion occurred and determine the next steps for repairs. 
Results of the information gathered today should be available Thursday. Photos of the various activities conducted at the bridge can be found on NCDOT’s Flickr site.

As part of today’s testing, crews with NCDOT’s Location and Surveys Unit conducted an underwater sonar survey of the area around Bent 166. Dive crews also inspected the area to assess if the sand is compacting as it needs to in order to properly support the bridge.

The department also began testing how much weight the bridge piles can carry. Carolina Bridge Company Inc. will drive two test piles into the inlet floor near the general vicinity of Bent 166. As of 4:30 p.m., they had completed one test drive.

NCDOT’s geotechnical staff will use the data gathered today, as well as additional surveys, to fully assess this situation and future repairs. Once a full assessment of the bridge’s safety is complete, NCDOT will determine the next steps. According to NCDOT Division 1 Engineer Jerry Jennings, the timeframe for reopening the bridge could be about a week from now or up to 90 days, depending on the findings of the assessment and timeline for repairs.

Approximately 30,000 cubic yards of sand were pumped during the weekend from the main navigation channel of the Oregon Inlet to the location at Bent 166 underneath the Bonner Bridge where scour, or the erosion of sand from bridge pilings, caused NCDOT to close the bridge on Tuesday, Dec. 3.

Emergency Repairs
NCDOT awarded a $1.6 million contract to Carolina Bridge Company Inc. of Orangeburg, S.C. last week for emergency repairs on the Bonner Bridge.

Crews will use sandbags and four-foot tall A-Jacks to provide support to the bridge pilings and prevent further scour from occurring. A-Jacks interlocked together will be placed around the perimeter of the support structure at Bent 166. Crews will then place sandbags inside the line of A-Jacks. An additional two layers of A-Jacks and sandbags will then be placed on top of the base layer for a total of 10-12 feet of additional protection. This will allow sand to collect over the sandbags and A-Jacks, providing additional support to the structure.

Contractor crews have begun mobilizing equipment and materials to the bridge site. NCDOT and the contractor are working together to develop a timeframe for the repairs to be complete.

Emergency Ferry Route
NCDOT’s Ferry Division activated its emergency route between Stumpy Point and Rodanthe with limited service the night of the bridge closure. The route went into full operation Wednesday, Dec. 4, with steady traffic and short-to-moderate wait times reported at both terminals. Dare County Emergency Managementhas issued a priority loading list for the route. The emergency ferry route will continue seven days a week as long as service is needed. Ferry information is available on the Ferry Division website, by calling 800-293-3779, or via Facebook and Twitter at @NCDOT_Ferry.

For More Information
NCDOT will continue to update the public on this situation online and via its N.C. 12 Facebook page and N.C. 12 Twitter account.

Permanent Replacement
While NCDOT is working hard to reopen the Bonner Bridge to traffic as quickly as possible, the emergency repairs are not considered a permanent fix for the aging bridge. After 50 years of weathering many storms, the bridge needs to be replaced. In July 2011, NCDOT awarded a $215.8 million contract for the design and construction of a new bridge. Design work began immediately and construction of the new bridge was set to begin in early 2013; however, lawsuits have put the project on hold.

Wednesday, April 3, 2013

Buxton

We understand that ocean overwash along N.C. 12 in the Outer Banks often makes it difficult for residents, visitors and businesses to get where they need to go efficiently. The state of emergency declared by Gov. McCrory helps us move forward with a short-term solution to protect this critical coastal highway at its most vulnerable location – the S-Curves.

Overwash at the S-Curves in March 2013
Currently, when overwash occurs at the S-Curves, it often forces N.C. 12 to close, making it challenging for people to get to jobs, education or medical appointments. A series of storms, including hurricanes Irene and Sandy, severely eroded the beach just north of Rodanthe.  Without the beach to act as a buffer, the strong surf threatens to undermine the structure and safety of the road.

That is why we have acquired $20.8 million in Hurricane Sandy emergency repair funds from the Federal Highway Administration to rebuild the beach at the S-Curves. Nourishment will provide much-needed protection to N.C. 12 until we can put a long-term solution in place in the coming years.

Although Buxton also experiences overwash, it was not included in the emergency declaration for several reasons. When overwash occurs, it washes water and sand onto N.C. 12, but it does not currently threaten the road’s integrity. Following recent storms, our crews have cleared the overwash off the road quickly without requiring repairs. In addition, N.C. 12 at Buxton does not qualify for federal emergency repair funds, and is not a candidate for state transportation funding for repair and protection at this time.

We have identified the section of N.C. 12 in Buxton as a “hot spot” that may see increased erosion in the future. We are studying this location to determine feasible long-term options for maintaining transportation along N.C. 12 if future conditions threaten the long-term viability of the existing roadway.

Tuesday, March 26, 2013

State of Emergency for NC 12 After Storms, High Surf

On March 19, Governor Pat McCrory declared a state of emergency for N.C. 12 in Dare County to help the N.C. Department of Transportation move ahead with a short-term solution to protect the critical coastal highway from frequent ocean overwash caused by high winds and strong surf.

The declaration comes at the recommendation of Transportation Secretary Tony Tata, following a visit and town hall meeting along the Outer Banks on March 11. The governor and secretary surveyed the area and talked with residents about having a more reliable route between Hatteras Island and the mainland.

“The people there have real concerns about the road they depend on to get to work, school or medical appointments,” said Governor McCrory. “They need a highway that is not forced to close every time a storm approaches. By declaring a State of Emergency, NCDOT can fast-track work to rebuild the beach along the S-Curves, so we can keep the road open until a long-term solution is in place.”

A series of storms, including Hurricane Sandy last fall, resulted in severe beach erosion along N.C. 12 at the S-Curves.





NCDOT has already executed an agreement with the U.S. Army Corps of Engineers to nourish the beach along the S-Curves. NCDOT is currently working closely with the N.C. Department of Environment and Natural Resources to swiftly acquire the permit needed to conduct the work. The target date to begin beach nourishment is mid-to-late spring.

NCDOT has also acquired $20.8 million in Hurricane Sandy emergency response funding from the Federal Highway Administration to pay for the beach nourishment. The one-time emergency response effort will fortify the section of N.C. 12 most often threatened by powerful winds for three years by which time a permanent solution should be built.

“We know this work can’t wait. N.C. 12 is an important pipeline for visitors who have a major impact on the local and statewide economy.” Secretary Tata said. “We want to ensure residents get the help they need now as we continue to look for innovative and strategic ways to make a lasting impact.”

At this time, NCDOT is considering two long-term solutions for the S-Curves, a roughly one-mile section of N.C. 12 just north of Mirlo Beach. They include a bridge within the existing easement and a 2.5-mile bridge that extends into the Pamlico Sound. The department will hold public meetings about the options this summer and plans to award a contract for construction this fall.

In early March, strong winds pummeled the Outer Banks, causing significant overwash at the S-Curves and forcing the road to close on and off temporarily for more than a week. NCDOT crews have reopened the road and are now in the process of replacing the sand that blew off the sandbags installed after Hurricane Sandy last year.






Wednesday, December 5, 2012

NC 12 Plan Q&A

Q&A about Hurricane Sandy Recovery Efforts along N.C. 12

We’ve gotten a variety of questions about our recovery plans along N.C. 12 in Dare County. We want to answer those questions, so you can better understand why we’re doing what we’re doing.

Q: Why are you rebuilding N.C. 12 in the same place?
A: We’re rebuilding N.C. 12 in the same location at the S-Curves, because it is the fastest way to restore access from Hatteras Island to the mainland. We know it hasn’t been easy for residents and visitors to use the emergency ferry route and the four-wheel drive route to get where they need to go. That is why we’re committed to reopening the highway to all vehicles as quickly as possible. Our goal is to have traffic flowing on N.C. 12 on or by Dec. 25.

Q: Are you considering beach nourishment at the S-Curves?
A: Yes. Beach nourishment is currently under consideration as we work to rebuild and reopen N.C. 12 near Mirlo Beach. We’re working with the U.S. Army Corps of Engineers to evaluate this option. No final decision has been made yet.

Q: Can you put down mats on the four-wheel drive route?
A: It is possible to put mats on the soft sand; however, they will only stabilize the route for four-wheel drive vehicles. The mats will not provide a surface stable or level enough for all-wheel drive and two-wheel drive vehicles. Therefore, we have chosen at this time not to use mats, because they would not greatly enhance the level of service we can provide, and they would take a great deal of effort to maintain.

Q: Can you put down gravel on the four-wheel drive route? Why not pave the four-wheel drive “sand road” and put dunes to the east of it?
A:  If we put down gravel or asphalt on the four-wheel drive route, we would be creating a permanent structure on Pea Island that is not inside our property lines. To do that, we would need to get special approval from a number of regulatory agencies. In addition, if we built a road on a new location, we would also need to build a temporary bridge at the overwash area to ensure access during storms. These combined steps would take far longer to implement and open to traffic than our current plan of rebuilding N.C. 12 in the same location, which should be complete on or by Christmas Day. Our goal is to reopen the highway as quickly as possible.

Q: Do you have long-term plans for the S-Curves?
A: Yes. In Rodanthe, the department is considering two options. The first one includes elevating N.C. 12 onto a bridge within the existing easement, which would end just north of the community center and not require beach nourishment. The second option is constructing an approximately 2.5-mile bridge that would extend into the Pamlico Sound and connect back to Rodanthe just north of the community center. These long-term solutions are currently moving through the environmental planning process required by the state and federal governments. We plan to award a contract for construction in the fall of 2013. 

Visit our new N.C. 12 webpage for more information.

We Have a Date!

Calm weather conditions have prevailed in Dare County and our crews have made significant repairs to N.C. 12 and we are now able to move to the next step - a   temporary solution to reconnect all traffic on Hatteras Island to points north of Mirlo Beach. This will be a multi-step process that will include installing sandbags, reconstructing dunes, and rebuilding the road near Rodanthe where Hurricane Sandy and a pair of Nor’easters damaged the highway.

What's Happening Now

Crews are currently placing 15-foot-long sandbags along a 0.4-mile section of N.C. 12 at the S-Curves just north of Rodanthe on Pea Island. In all, 1,800 new sandbags will go in to create a protective barrier between the ocean and the road. Once the sandbags are in place, we'll rebuild the dunes on top of the sandbags.

At the same time, broken pavement will be hauled off from this section of N.C. 12. After sandbags are installed at the most heavily damaged parts of the highway, crews will begin rebuilding the road where it was located before the series of storms hit. And as you know, all work is heavily dependent on the weather and tidal conditions.

Weather permitting, we hope to open the newly paved lanes of N.C. 12 to all traffic on or by Dec. 25. Until then, four-wheel drive vehicles must continue to pass through checkpoints at the temporary bridge on Pea Island and Mirlo Beach to travel between Hatteras Island and the mainland.

Motorists are reminded that any private vehicle larger than a one-ton truck cannot use the route in order to protect access and allow traffic to flow more efficiently. In addition, private trucks with trailers are not permitted. Two-wheel drive vehicles are not allowed on the route under any circumstance.
More information on N.C. 12 recovery efforts is available on our N.C. 12 Recovery webpage and N.C. 12 Facebook page. For the latest details on the emergency ferry route, as well as schedules for our regular ferry routes, call 1-800-BY-FERRY and press 1, or visit the NCDOT Ferry page.

Friday, November 16, 2012

Thanksgiving

Due to extreme weather conditions, N.C. Department of Transportation crews are unable to complete anticipated repairs to N.C. 12 in Dare County in order to have the road open for Thanksgiving travelers.

“Unfortunately NCDOT crews have been at the mercy of the weather and we are not where we want to be in terms of reopening N.C. 12,” said NCDOT Division Engineer Jerry Jennings. “With recent weather conditions and another forecasted Nor’easter on the way, we will be unable to fully reopen N.C. 12 by Thanksgiving, but are working with the Ferry Division to accommodate the demands of holiday travelers.”

High winds and overwash along N.C. 12 are causing intermittent closures to four-wheel drive access on Pea Island. These closures often occur with very little advanced notice due to rapidly changing weather and surf conditions. When a closure happens, NCDOT must wait for conditions to improve before reopening the route to ensure motorists safety.

Based on current conditions, the route may only be open during low tide. For updated tide information and conditions, visit the National Oceanic and Atmospheric Administration webpage. To find out the status of the route, call 511, visit our travel information webpage, or follow NCDOT on Twitter or Facebook.

When weather conditions are not causing closures, the four-wheel drive route is scheduled to be open from 5 a.m. to 10 p.m. Because of hazardous driving conditions, Dare County first responders will escort drivers before dawn and after dusk when the road is accessible to traffic.

Drivers of four-wheel drive vehicles should expect a rough ride, which will include traveling over sand, damaged pavement and some water. On the sandy portions of the route, they will follow lane markers comprised of barrels, cones and/or flags.

NCDOT asks motorists to follow these important safety measures on the four-wheel drive access:
•Only drive four-wheel drive vehicles with a high ground clearance. Cross-over four-wheel drive vehicles that are lower to the ground may get stuck in the rugged terrain;
•If you drive at night, use extreme caution. There will be no lights staged along the route, so your vehicle’s headlights will offer the only way for you to see;
•Drive slowly; 
•Pay close attention to the temporary traffic signals; and
•All four-wheel drive vehicles are encouraged to lower tire pressure to minimize the chances of becoming stuck.

In addition to the four-wheel drive access, NCDOT’s Ferry Division has added extra departures from each side on its Swan Quarter-Ocracoke route beginning Saturday, Nov. 17 through Monday, Nov. 26, to accommodate holiday traffic demand.

The additional departures include: 
  • Departing Swan Quarter at 7 a.m. and 1 p.m.; and
  • Departing Ocracoke at 10 a.m. and 4 p.m.

As a reminder, the regular fall schedule on the Pamlico Sound is:

  •  Departing Cedar Island and Ocracoke at 7:30 a.m., 10, 1 p.m. and 4;
  • Departing Swan Quarter at 10 a.m. and 4 p.m.; and
  • Departing Ocracoke to Swan Quarter at 7 a.m. and 12:30 p.m.

Ferry reservations can be made online or by calling 800-293-3779 (BY-FERRY) and pressing 2. Ferry information is available via Twitter . To help travelers gauge the amount of traffic waiting to ride the ferry, visit the live webcams Dare County has stationed at Rodanthe and Stumpy Point. The cameras cannot show priority order, but they can offer a real-time look at number of vehicles in line.

More information on N.C. 12 recovery efforts is available on our N.C. 12 webpage and N.C. 12 Facebook page. For the latest details on the emergency ferry route, as well as schedules for our regular ferry routes, call 1-800-BY-FERRY and press 1, or visit the NCDOT Ferry page.

Tuesday, March 6, 2012

Bonner Bridge Repairs Start Today



Our crews started making repairs this morning on the Herbert C. Bonner Bridge, which carries N.C. 12 over Oregon Inlet in Dare County.


They will repair, clean and paint the steel girders that make up three spans of the high-rise portion of the bridge over the main channel. Crews will cut out deteriorating sections of the girders and replace them with new steel. Once the new steel is in place, they will paint it to protect it from the elements.

How do you work on a bridge, over  an  inlet? Our workers will stand on decking placed under the bridge. Special tarps will catch any of the old paint that falls off the bridge during the project  to protect the environment.


The decking will reduce the vertical clearance for vessels traveling through the navigational channel in the Oregon Inlet from 65 feet to 61 feet. The N.C. Department of Transportation is working with the U.S. Coast Guard to inform mariners of the temporary change.


The work was originally scheduled to start last September but it was postponed until this week because of the aftermath of Hurricane Irene. Weather permitting, the work is should be complete by May 22.

The repair work will close one lane along a one-quarter mile section of the bridge over the main channel. During the first few days of the project, the lane closure will be in place during daylight hours only. Following that period, it will go into effect 24 hours a day, seven days a week. Look for  portable traffic signals to guide motorists through the work zone. If you're headed that way, be sure to allow  additional time to reach your destination and go slow and pay attention in the work zone.

Astron General Contractors  is working with NCDOT on the $741,000 project.